Working for Concord Medical Centre in South Gloucestershire, we delivered a new three-storey extension and remodelling of existing accommodation space, including new treatment rooms, offices and pharmacy accommodation.

Construction planning and logistical arrangements were key in the successful delivery of this project of complex and exacting specification requirements.

Key Facts

0m
retaining structure
0
manufactured & installed internal door sets
0
m2 precast flooring

The initial phase of enabling works included a 3 metre high retaining wall along the perimeter of the site to facilitate the construction phases.

The project scope was to deliver high-quality consulting rooms, patient waiting areas, office space, and pharmacy area prepared for client fit-out. Installation of a range of energy efficiency systems completed the build.

Our teams worked in live and sensitive environments, with restricted access to the site working area. Due to the confines of the site, deliveries were planned on a just-in-time-basis to minimise disruption and ensure site productivity.